Single Beam Gantry Crane 5 Ton Installation - Gantry Crane Case


Single beam gantry crane 5 ton for Saudi Arabian electric plant. Check 5 ton single girder gantry crane installation procedure . Design your gantry crane!

Gantry crane main parameters

  • Type of crane:electric single beam gantry crane
  • Lifting capacity of single beam crane: 5tons
  • Lifting height of single beam gantry crane: 16 meters
  • Span of single beam gantry crane : 30meters

Profile of Saudi Arabia Electric Power Plant

Saudi Electricity Company ("SEC"primary )'s activity is the generation, transmission, and distribution of electricity within the Kingdom - the GCC's largest economy. It is the largest producer of electricity in the Kingdom and the sole owner of the entire transmission and distribution network, which serves all types of consumers. The Saudi government owns the vast majority of Saudi Electricity Company.

Electric Power Plant of Saudi Arabia client

Electric Power Plant of Saudi Arabia client

We fly from Beijing to Abu Dhabi before arriving in the Saudi Arabian city of Jeddah. How is the single beam gantry crane set up? The on-the-spot report will be digested for your reference in this section.

Work out the installation plan for the single beam gantry crane

When we first met the customer, we went to the single beam gantry crane installation site with him. Then we made a plan for how to install the single beam gantry crane and how many days it would take to complete the job, etc.

1. The process how to install the single beam gantry crane:

  • Install the gantry crane travelling rail, installed on the ground.
  • Connect the end carriages and bottom beam
  • Set up the supporting gantry legs.
  • Lift up the main girder and installed the gantry hoist
  • Assembly the main beam of the gantry crane on the supporting legs
  • Electrical works

2. The gantry crane installation is expected to take 15 days.

3. Installations workers and tools

  • Workers needed: at least two welders, four mechanical workers, two electrical workers, one driver to control the 30 ton truck crane, and one driver to control the boom lift/scissor lift.
  • Tools required: 4.0 lever weld rod, four chain blocks with a minimum capacity of one ton, and a toolbox containing a wrench, spanner, screw driver, welding machine, and other items.
  • We begin work immediately after confirming the above details.

Gantry Crane Rail Installation

  • Then we installed the four side rails for gantry crane with the help of workers.
  • Because the wheel load on the 5 tons and 30m/20m span gantry crane is heavy, we chose the P38 rail for the customer. Platens and bolts secure the P38 rail to the ground.
  • After that, we'll start connecting the bottom beam and legs.

Single beam gantry crane rail installation

Single beam gantry crane rail installation

Bottom beam and legs connections

  • First and foremost, each gantry crane has two bottom beams and four legs. This means that one bottom beam must connect two legs.
  • ·Connections by bolts also.
  • Place the bottom beam on the ground with enough space between them, then lift the legs up and slowly move them towards the bottom beam directions. When you want to keep the hole between the bottom beam and the legs in the same place, use one steel stick to hold it in place and connect all the holes quickly with bolts. After all holes have been bolted together, shake it to see if the connection is stable. If everything is fine, repeat with the other leg.
  • The engineer must then measure the distance between the two legs. This distance must be the same as the saddle of the main girder.
  • If the distance is acceptable, locate one box iron and weld it to the legs to ensure the distance was maintained steadily while lifting up.
  • The bolts,clamps, and platens installed for the 5 ton single beam gantry crane secure the rail.

Bottom beam and leg of gantry cranes are bolted together

Bottom beam and leg of gantry cranes are bolted together

Lifting and setting the legs up on the rail

  • After connecting the two side legs and bottom beams, the girders must be installed on the rail. It would be best to set up legs on a small wind day.
  • Finding the center of the welded box iron on the two legs and fixing it with the truck chain, then slowly lifting it up and placing it on the rail.
  • After lifting the left two legs, we must use wire rope and chain to secure the center of the box iron. One of the left two legs requires two chain block fixes on each side. If this one doesn't work, try another.

Setting up the supporting legs of gantry crane by truck crane

Setting up the supporting legs of gantry crane by truck crane

Fix the hoist on the bottom of main girder

  • Allow the truck crane to lift the main girder to a height of 1.5 meters above the ground. Ship the hoist to the bottom of the main girder and tighten it up.
  • Connect the cables, limit switch, and so on.

Lift and fix the main girder on the top of legs

  • When there is one good position between the legs and the main girder, we must use the truck crane to slowly lift the main girder up and find at least two people to climb to the upside of the legs. Each side's two people must ensure that the main girder edge is in the side of the bolts. Then lower it and allow the welder to weld the girders and legs. Before we can remove the truck crane, we must weld at least two spaces on each connection side.
  • When all of the welds are completed, the mechanical work is completed.

Gantry Crane installation: Shipping main girder and equipped the gantry crane on the main girder & Lifting main girder up on legs

Gantry Crane installation: Shipping main girder and equipped the gantry crane on the main girder & Lifting main girder up on legs

Electrical works

  • The engineer will direct the electrical workers as they work with the help of a boom lift.
  • We must test and commission the crane after all mechanical and electrical work is completed.

Single girder gantry crane finished installation

Parts of Clients Reference List in Saudi Arabia

  • M***e Services Co. Ltd for S**C company: single beam gantry crane5 Ton -30M H=12M,
  • Q***r R***a Y***f Construction Co. Ltd.: single beam gantry crane 10 Ton-15M H=6M,
  • D***q E**t for contracting: single beam overhead crane 3 Ton-8.9M H=9M, Pillar jib crane 1 Ton-4M H=5M, Pillar jib crane 1 Ton-2.5M H=5M ,
  • Business S***d Trading Corp.: Electric wire rope hoist 0.5 Ton H=9M ,
  • A***I TRADING COMPANY: single beam gantry crane 8 Ton-17M H=8M ,
  • Arabian M***l Industries Ltd.: Pillar jib crane 2 Ton-2.6M H=1.4M,
  • ALI AL-***N C***TING EST.: single beam overhead crane 10 Ton-24M H=12M
  • U***l Technical S***s Company: single beam overhead crane 5 Ton-11.18M H=5M,
  • S***h Al J***a C***ting Co. : single beam overhead crane 5 Ton-12.5M H=5M,
  • A***d B***s Machines Co. : Electric winch 3 Ton H=200M,
  • O***n Arabian P***ing Company :Electric wire rope hoist 5T H=10M,
5 ton single beam gantry crane for sale Saudi Arabia finished installation

Single Girder Gantry Crane installation in Saudi Arabia - Gantry Crane Projects

Article by Bella ,who has been in the hoist and crane field since 2016. Bella provides overhead crane & gantry crane consultation services for clients who need a customized overhead travelling crane solution.Contact her to get free consultation.